United States · Demonstration Reactors

After Safety Analysis Approval Comes the Readiness Review: The Steps Radiant and Last Energy Demonstration Reactors Pass Before Startup

Antares holds an NSDA approval while Last Energy and Radiant hold DSA approvals; the next gate is a DOE readiness review of equipment, procedures and people.

In October, three U.S. demonstration reactor projects announced safety approvals from the Department of Energy (DOE) one after another. It is tempting to read that news as a sign that the reactors are about to switch on. In practice, a reactor with an approved safety analysis still has a set of checks ahead of it before startup. This post follows DOE's published procedures step by step to show what those checks are.

Concept image of a compact demonstration reactor module inside a domed containment hall
Concept image created for this article from a text-free AI base with an English information layer.

Three Companies, Three Kinds of "DOE Approval"

On November 2, the American Nuclear Society (ANS) reported the October DOE authorization milestones of Antares, Last Energy and Radiant in a single article. The three companies are building different demonstration reactors, and each stands at a different stage.

  • Antares: On October 23, the company announced approval of the Nuclear Safety Design Agreement (NSDA) for its Mark-1 reactor. The NSDA is the first step, setting the design requirements and safety analysis methods. Antares plans to pursue a power demonstration at Idaho National Laboratory (INL) in 2027.
  • Last Energy: On October 7, the company announced approval of the Documented Safety Analysis (DSA) for its pilot reactor at Texas A&M–RELLIS, along with its entry into the readiness review (RR).
  • Radiant: On October 29, the company announced DSA approval for Kaleidos and named the readiness review as its next step.

All three carry the label "DOE approval," yet Antares is at the starting line of design, while the other two are at the gate of the readiness review. The name of the approved document tells you how far a project has come.

Flow from NSDA, PDSA, DSA and TSR, readiness review to startup approval with the three companies' positions
The DOE authorization path and where the three demonstration projects stand (Source: US-DOE DOE-STD-1271-2026, ANS, adapted)

From Design Agreement to Operating Limits: The Safety Basis Document Chain

The DOE standard DOE-STD-1271-2026 (dated September 2026 on its cover) links design, safety analysis and operation into a single pathway for nuclear facilities authorized by the Office of Nuclear Energy (NE). The full texts of the two projects' individual agreements and approval letters remain unpublished, so the explanation below follows the public NE procedure.

1. NSDA: The parties agree on applicable requirements, analysis methods, document formats and how regulatory interactions will work. The list of reference documents used for design and verification, the Code of Record, is managed from this point onward. 2. PDSA (Preliminary Documented Safety Analysis): The safety analysis is integrated during preliminary design, and equipment performance requirements are set. 3. DSA and TSR (Technical Safety Requirements): The safety basis reflecting the as-built facility is finalized, together with its operating limits. 4. RR and startup authorization: The readiness of people, equipment and procedures is confirmed, and findings are closed out.

The DSA is the blueprint of safety. It records which hazards and accidents the facility could face, what prevents and mitigates them, and within what bounds the facility must operate. Once DSA approval settles the safety case on paper, the question shifts to whether that case has been built into the facility as written.

What the Readiness Review Checks on Site

The readiness review follows directive NE O 425.1. For facilities within its scope, this directive takes over the role of the earlier DOE O 425.1E. The review plan (RP) covers the scope, the equipment under review, safety management programs, prerequisites, and field demonstrations, interviews and drills. A review can also be split by activity, for example fuel receipt, fuel storage and fuel loading. The directive recommends formal notification 90 days before the review begins and sets a 30-day standard for DOE approval of the review plan.

The review team looks at five broad areas:

  • Equipment and maintenance: safety functions, plus test and calibration records
  • Operating procedures: current revisions that reflect equipment changes
  • Personnel and organization: qualifications, demonstrations and interviews
  • Emergency response: drills performed and their effectiveness
  • Safety basis: on-site implementation of DSA and TSR provisions

The concept tying these together is configuration management, the work of keeping three things aligned: design requirements, the physical equipment and the documentation. Every change within the review scope must either be completed and closed, or carry an evaluation showing that safe startup remains unaffected. Open maintenance items also undergo an operational impact evaluation. If the DSA defines what must be protected, the readiness review asks whether the people, equipment and procedures are ready to protect it.

Control room walkdown with the five readiness review areas: equipment, procedures, people, emergency response and safety basis
The five areas a readiness review checks on site (Source: US-DOE NE O 425.1, adapted)

After Startup Authorization: Hold Points and the 60-Day and 150-Hour Targets

When the review is complete, the Startup Authorization Authority (SAA) confirms that pre-start findings are closed, that any needed compensatory measures are in place, and that a corrective action plan exists for items remaining after startup, and then grants approval. An appendix to the directive names the Secretary of Energy, or a delegate, as the authority for initial reactor startup.

After startup, operation expands in stages, beginning with the lowest-risk activities. The sequence moves through fuel loading, approach to criticality, physics testing and unrestricted operation. Between stages sit hold points, tests that must be completed successfully before the next activity begins. A Joint Test Group (JTG), bringing together experts in operations, systems, reactor engineering, nuclear safety and DOE oversight, confirms that the actual safety functions match the analytical predictions.

After a successful review, Radiant plans to load fuel and carry out staged power ascension testing at the DOME facility at INL. The company's targets are 60 effective full-power days (EFPD) of testing and 150 hours of continuous, full-power, hands-off operation. EFPD converts an operating record into the equivalent number of days at full power.

  • 60 EFPD: 60 days × 24 hours works out to 1,440 full-power hours of cumulative operation
  • 150 hours: 150 ÷ 24 works out to about 6.25 days of continuous operation

These two targets measure different things, how much operation has accumulated and how long it has been sustained without interruption, so each will get its own check once results are announced. Last Energy also says its pilot uses a core of the same scale as its commercial design, so once the approved operating envelope and test results are published, the basis for carrying the pilot over to the commercial design will become more concrete. As with the new NRC rule covered in our October 23 post, demonstration data serve as the starting point for commercial licensing.

Startup stages from fuel loading to unrestricted operation, with Radiant's 60 EFPD and 150-hour targets calculated
Staged startup testing and Radiant's test targets (Source: US-DOE DOE-STD-1271-2026, Radiant, adapted)

The next milestones to watch are official announcements that the two projects have completed their readiness reviews and begun testing.