Four Years on Paper, Eighteen on the Calendar — Finland's Olkiluoto 3, the First EPR

A fixed-price, four-year turnkey contract became an eighteen-year lesson in design, quality and rebuilding the ability to build.

In brief

In December 2003 Finland's TVO ordered the world's first EPR, a 1,600 MWe pressurized water reactor, for a fixed price of about €3 billion and a four-year build. Construction started in August 2005, but late design, quality problems and slow licensing of the digital control system stretched the job to almost eighteen years. Olkiluoto 3 entered commercial operation on 1 May 2023, and its lessons became a checklist for every country trying to build reactors again.

If the contract had come true

If everything had gone by the contract, this story would have ended in 2009. On Olkiluoto island, on Finland's west coast, Europe's most powerful reactor would have started sending power to the grid, and Western Europe would have had its proof that it could still build nuclear plants. The real calendar told a different story. Olkiluoto 3 entered commercial operation on 1 May 2023. A four-year construction promise had turned into a journey of almost eighteen years from the first day on site. [1]

The first order in fifteen years

The Finnish utility TVO (Teollisuuden Voima) already ran two boiling water reactors on the island. In May 2002 the Finnish parliament approved a fifth reactor for the country by 107 votes to 92. In December 2003 TVO ordered a complete new unit from a consortium of France's Framatome ANP (later Areva NP) and Germany's Siemens. It was a turnkey deal at a fixed price of about €3 billion (some sources say €3.2 billion): the supplier would hand over the keys, and any overrun would be the supplier's problem. [3]

The design was the EPR, the European Pressurized Reactor, which combined the latest French and German pressurized water reactor technology. It is a giant: about 1,600 MWe net from 4,300 MW of heat. Its containment has two walls, designed to withstand even an aircraft impact, and beneath the core sits a "core catcher" built to hold molten fuel in the unlikely event of a meltdown. As the first new nuclear order in Western Europe in roughly fifteen years, it became a symbol of what was then called the "nuclear renaissance".

Olkiluoto nuclear power plant across a lake with reeds in the foreground: a domed reactor building on the left and two tall red-and-white reactor buildings in the centre and on the right
Olkiluoto in July 2015: the domed building on the left is unit 3 (EPR), with units 1 and 2 in the centre and on the right. Source: Hannu Huovila / TVO, CC BY 3.0, resized, via Wikimedia Commons.

Ground broken, drawings not ready

The official construction start was 12 August 2005 (some sources give May or July 2005). Problems soon surfaced. Foundation concrete failed to meet specifications and cost several months. Large forgings from a subcontractor had to be made again. Welding defects turned up in piping and in the steel liner of the double containment.

In 2010 Jukka Laaksonen, director general of the Finnish regulator STUK, put his finger on the root cause: "In Olkiluoto 3 project, detailed design has been done too late." The construction time set in the call for bids, he wrote, "was therefore not realistic." He also warned that with a first-of-a-kind plant "one could expect thousands of smaller and bigger non-conformances." After decades without new builds in Western Europe, experienced nuclear designers and manufacturers who knew nuclear quality standards had become scarce. [4]

The longest hold-up was the digital instrumentation and control (I&C) system, the reactor's nervous system. STUK approved it only in April 2014. That February, Areva had sharply slowed work, citing among other things the unfinished automation design. The completion date slid to 2015, then to 2018, and kept sliding. [3]

Gantt-style chart comparing a planned 4-year schedule from 2005 to 2009 with the actual schedule from August 2005 to May 2023, about 14 years late, with markers for first criticality on 21 December 2021, grid connection on 12 March 2022 and commercial operation on 1 May 2023
Planned versus actual schedule of Olkiluoto 3. Illustration/reconstruction; dates from TVO and the World Nuclear Association.

Who got the bill?

A fixed price did not make the costs disappear. By the end of 2012, Areva itself estimated the total cost at about €8.5 billion. The consortium claimed €3.52 billion from TVO, and TVO counter-claimed €2.6 billion, in international arbitration. In March 2018 the dispute ended with a settlement under which the suppliers paid TVO €450 million. The final cost is estimated at about €11 billion: roughly €5.5 billion invested by TVO plus roughly €5.5 billion in losses for Areva. That figure is an estimate rather than an audited total, and numbers differ between sources. [3] [5]

Bar chart of cost estimates: about 3.0 billion euros in the 2003 contract, about 8.5 billion in Areva's end-2012 estimate, and about 11 billion in the final estimate split into 5.5 billion TVO investment and 5.5 billion Areva loss, next to five cards listing causes of delay
From a contract price of about €3 billion to a final estimate of about €11 billion (nominal; figures vary between sources), with five causes of delay. Illustration/reconstruction based on WNA, WNISR 2019 and Power Engineering (2010).

Lights on at last, and one more test

The government granted the operating licence in March 2019, and the 241 fuel assemblies were loaded in spring 2021. The reactor first went critical on 21 December 2021 and first fed electricity to the grid on 12 March 2022. Even then the finish line kept moving. In October 2022, cracks were found in the impellers (the spinning blades that push water) of all four feedwater pumps, and the parts had to be replaced with sturdier ones. Regular electricity production finally began on 16 April 2023, and commercial operation on 1 May 2023. [1] [2]

TVO says that about 30 percent of Finnish electricity is produced at Olkiluoto. Its chief executive, Jarmo Tanhua, put it simply: "The production of Olkiluoto 3 stabilises the price of electricity." In 2025, nuclear power supplied about 40 percent of Finland's electricity. [2] [3]

A digital display in a visitor centre showing OL 1 at 894 MW, OL 2 at 892 MW and OL 3 at 0 MW
The live output display at the Olkiluoto visitor centre on 3 April 2024: unit 3 shows 0 MW during its first annual outage. Source: Antti Leppänen, CC BY 4.0, resized, via Wikimedia Commons.

That "0 MW" is a fitting footnote. The first annual outage, which began on 2 March 2024, was planned for 37 days and took 74. A first-of-a-kind plant keeps teaching lessons even after it starts running.

The weight of being "first"

Olkiluoto 3 was the first EPR to begin construction, but not the first to run commercially. That record went to China's Taishan 1, on 13 December 2018. France's Flamanville 3, started in 2007, was connected to the grid only in December 2024 and reached full power for the first time in December 2025. The first AP1000 units built in the United States went through similar delays. [6] [7]

Flamanville nuclear power plant seen from the sea, with the large EPR unit 3 building in the foreground on the rocky coast and older units behind
Flamanville seen from the sea, with unit 3 (EPR) in the foreground. Source: JKremona, CC BY-SA 4.0, resized, via Wikimedia Commons.

The lesson of Olkiluoto 3 is less about the technology than about the ability to build again. Finish the design before you pour concrete. Rebuild broken supply chains and skilled workforces. And even under a turnkey contract, the owner must keep a firm grip on the project. Laaksonen's list became a checklist for countries preparing their own new reactors. [4]