Policy, Economics & Reactor Types · C-PE-003

Nuclear Generation Cost and Economics — Capital, O&M, Fuel and the Discount Rate Behind the LCOE

Why a capital-intensive source lives or dies by the discount rate: 53.3 USD/MWh at 7 % for a new ALWR in one OECD/NEA-IEA 2020 case, 39.4 at 3 % and 67.2 at 10 %.

Definition

Generation cost is the total cost a plant incurs over its life expressed per kWh (or MWh) generated. Comparisons use the levelized cost of electricity (LCOE): the constant unit price at which the present value of discounted total costs equals the present value of discounted generation.

Nuclear power is capital-intensive, with a large capital share and a small fuel share. That is why the discount rate, construction time and capacity factor decide its economics.

Principle and mechanism

Components of generation cost

ComponentContentNuclear characteristic
Capital costConstruction cost (overnight) + interest during construction (IDC), annualized over the lifeLargest share
O&MLabor, maintenance, insurance, levies; fixed and variable partsMostly fixed
FuelFront end (concentrate, conversion, enrichment, fabrication) + back end (storage, disposal)Small share
Decommissioning and back-end liabilitiesFunded during operationInternalized through regulated unit charges
Carbon costCost of fossil emissionsNot applicable

Capital cost and carrying charges

  • Overnight cost: the construction cost assuming the plant were built overnight. It consists of direct and pre-construction costs, indirect costs (engineering, management), owner's costs and contingency; the OECD default contingency for nuclear is 15 %.
  • Investment cost = overnight + IDC (+ escalation in real projects). With a 7-year build and a 7 % discount rate, IDC is about 28 % of the overnight cost.
  • Carrying charges: the annual fixed cost of keeping invested capital, made up of return on capital (interest, dividends), depreciation, taxes and insurance. It is the investment times the fixed charge rate (FCR); without taxes and insurance it equals the capital recovery factor CRF = r(1+r)ⁿ/[(1+r)ⁿ−1]. The interest on money tied up in fuel inventory goes by the same name.

The LCOE equation and its terms

Stacked bars of LCOE at a 7 % discount rate for example new plants (one OECD/NEA-IEA 2020 country case): nuclear ALWR 1,377 MWe 53.3 USD/MWh (investment 25.5, O&M 18.4, fuel 9.3, decommissioning 0.03), coal USC 954 MWe 75.6 (investment 12.9, O&M 11.6, fuel 27.5, carbon 23.6), LNG combined cycle 982 MWe 86.8 (investment 9.7, O&M 8.4, fuel 58.2, carbon 10.3); a mini chart of nuclear LCOE at 3, 7 and 10 % (39.4, 53.3, 67.2) with investment shares of 29, 48 and 59 %; and the LCOE equation
LCOE structure of example new plants (one OECD/NEA-IEA 2020 country case, 7 % discount rate, 85 % capacity factor, carbon 30 USD/tCO₂, 2018 USD). Illustrative inputs, not market prices.

LCOE = Σ(Iₜ + O&Mₜ + Fₜ + Cₜ + Dₜ)(1+r)−t / Σ Eₜ(1+r)−t

I is investment, O&M is operation and maintenance, F is fuel (including the back end), C is carbon cost, D is decommissioning, E is generation and r is the real discount rate. If construction spending is placed directly on the time axis, IDC is not added separately. The denominator is discounted because what is discounted is not the MWh itself but the value of the revenue from that MWh (OECD/NEA-IEA 2020). Decommissioning looks small in the LCOE at 0.03 USD/MWh, but only because spending 60 years in the future is discounted.

Worked example (assumptions stated)

The assumptions are one set of OECD/NEA-IEA 2020 country inputs for a new ALWR (1,377 MWe): overnight 2,157 USD/kWe (2018 USD), 7-year construction with even spending, 60-year life, 85 % capacity factor, r = 7 %, O&M 18.44 and fuel 9.33 (front end 7.00 + back end 2.33) USD/MWh.

  1. Investment: mid-year spending compounded to the completion date → 2,758 USD/kWe (IDC 27.9 %)
  2. CRF (7 %, 60 years) = 0.07×1.07⁶⁰/(1.07⁶⁰−1) = 0.0712
  3. Annual capital cost = 2,758 × 0.0712 = 196.5 USD/kW·yr
  4. Annual generation = 8,760 h × 0.85 = 7,446 kWh/kW
  5. Capital cost per unit = 196.5 / 7.446 = 26.4 USD/MWh
  6. LCOE ≈ 26.4 + 18.44 + 9.33 + 0.03 (decommissioning) ≈ 54.2 USD/MWh

The difference from the OECD table value of 53.3 comes from the discounting-time convention (mid-year vs end of year).

Fuel cycle cost: direct and indirect

  • Direct costs: actual spending on materials and services. The nine elements of a recycle fuel cycle are (1) purchase of uranium concentrate, (2) conversion (UF₆), (3) enrichment (SWU), (4) fabrication, (5) spent fuel transport, (6) reprocessing, (7) recovered uranium conversion and credit, (8) plutonium credit (or MOX fabrication), and (9) treatment and disposal of high-level waste.
  • Indirect costs: carrying charges (interest, taxes) on inventory and in-process material tied up for several years from purchase through discharge and credit recovery. The gap between spending time and burn time is reflected by discounting and compounding.
  • Example (WNA, September 2021 prices): for 1 kgU of fuel, uranium 51 %, conversion 7 %, enrichment 24 % and fabrication 18 %, totalling 1,663 USD, or about 0.46 ¢/kWh at 45 GWd/t.

Influencing factors and sensitivity

LCOE against real discount rate from 0 to 16 % for nuclear (solid), coal (dashed) and LNG combined cycle (dotted), with OECD table points at 3, 7 and 10 % (nuclear 39.4, 53.3, 67.2), crossovers of nuclear with coal at about 13.9 % and with LNG at about 15.1 %, a tornado chart of nuclear LCOE around 53.3 for discount rate (39.4 to 67.2), overnight cost (45.7 to 61.0), capacity factor (48.7 to 62.7) and construction time (51.5 to 56.3), and a photo of a plant under construction
LCOE sensitivity, reproduction model of one OECD/NEA-IEA 2020 country case. The crossover discount rates hold only for these assumptions; above 10 % the curves are extrapolated.
Variable (base 53.3 at 7 %)RangeNuclear LCOE
Discount rate3 ↔ 10 %39.4 – 67.2
Overnight cost−30 ↔ +30 %45.7 – 61.0
Capacity factor95 ↔ 70 %48.7 – 62.7
Construction time5 ↔ 10 years51.5 – 56.3

Only one variable was changed at a time. The construction-time range is a lower bound that reflects IDC only (real delays also raise the unit cost), and the capacity-factor range assumes O&M is a fixed cost. Within these ranges the discount rate has the largest effect.

Choosing a power source by discount rate: the discount rate represents the cost of capital and project risk. The higher it is, the less future fuel savings are worth, and the more nuclear is disadvantaged. Plot the LCOE (or the present value of revenue requirements) of each candidate as a function of the discount rate and find the crossover discount rate r. If the project discount rate is below r, nuclear is favored; above it, fossil is favored. Then recheck by varying fuel prices, carbon prices and capacity factor. In the model above, nuclear and coal cross at about 13.9 % and nuclear and LNG combined cycle at about 15.1 % (for these assumptions only).

What it means in a plant

A market settlement price (energy price plus any capacity payments) is not a generation cost: it reflects market rules, not the plant's capital, O&M and fuel costs.

Economic factors compared with fossil fuels

FactorNuclearCoal, LNG
Cost structure (7 %)Investment 48 %, O&M 35 %, fuel 18 %Coal: fuel + carbon 67 %; LNG 79 %
Discount rate and construction timeSensitiveLess sensitive
Fuel price swingsSmall effect, easy to stockpileLarge effect
Carbon priceNoneDirectly in the unit cost
ResourcesSmall amounts of uranium, stockpiledImport-dependent, bulk transport

On the OECD 2020 medians, new nuclear is cheaper than fossil at 3 %, and can be more expensive than fossil at 7 and 10 %. In the example inputs used here, nuclear remains the cheapest up to 10 %. Long-term operation (LTO) is at the lowest level of all sources.

External and system costs

  • External costs: the EU ExternE results in €cent/kWh are nuclear 0.2–0.7, coal 2–15, gas 1–4 and wind 0.05–0.25. Accident risk and long-term waste management are partly internalized through levies, provisions and the nuclear damage compensation system.
  • System costs: the LCOE is a busbar cost, so it leaves out transmission and distribution and the backup and balancing costs of variable sources. Complementary indicators such as VALCOE are used alongside it.

Methodology reference

  • OECD/NEA-IEA Projected Costs of Generating Electricity 2020: LCOE methodology. It is the 9th edition since 1983, and as the series was discontinued afterwards, it is the latest.

Easily confused pairs

AB
Market price vs generation costMarket settlement value (energy price, capacity payments)Actual cost (capital, O&M, fuel)
Overnight vs investment costConstruction cost without interestOvernight + IDC
CRF vs FCRCapital recovery (interest + repayment)CRF + taxes and insurance
Direct vs indirect (fuel)Spending on concentrate, enrichment, fabrication, etc.Carrying charges on inventory

Key points at a glance

  1. Definition: the unit price at which the present value of discounted lifetime costs equals the present value of discounted generation times that constant price.
  2. Equation: LCOE = Σ(I + O&M + F + D)(1+r)−t / Σ E(1+r)−t.
  3. Components: capital (overnight + IDC, annualized with the CRF), O&M, fuel (front + back end), decommissioning and back-end liabilities.
  4. Nuclear structure: in the example inputs at 7 %, investment 48 %, O&M 35 %, fuel 18 % — capital-intensive.
  5. Influencing factors: discount rate (39 → 67 USD/MWh from 3 → 10 %), construction time (IDC), capacity factor (spreading fixed costs), construction unit cost.
  6. Source selection: below the crossover discount rate r* on the LCOE–discount-rate curves nuclear is favored; above it, fossil.
  7. Price vs cost: a market settlement price is not a generation cost; state the assumptions behind any cost figure.
  8. Limits: transmission, grid and external costs are excluded → also examine system and external costs.
Sketch: LCOE against discount rate with a steep nuclear line and a shallow dashed coal line crossing at r*, nuclear cheaper to the left and coal cheaper to the right, beside the LCOE formula and its cost components
Sketch: choosing a power source by discount rate (schematic, straight-line simplification).